[Everyone] Power Main
Lauren Rich
laureninatlanta at gmail.com
Wed Feb 25 21:36:22 UTC 2026
Hi ron -
I shared w dave yesterday by email that a 3rd pty contractor from ga power
approached me yesterday as i was leaving, he wanted to speak and meet w our
assoc pres as ga power intends to replace our underground lines (they go
back to 1984). I m not sure dave is in town, i will give him a call. The
contractor told me they want to start next week; worst case is it could
take 2 weeks. I do not know what they will have to dig up to do this. I was
assured by him that we won't lose power during this time.
Lauren Rich
Atlanta, GA
On Wed, Feb 25, 2026, 3:03 PM Ronald Baggett via Everyone <
everyone at chelseaplacedecatur.com> wrote:
> Hi everyone, saw a guy marking the property and he said GA Power was going
> to replace the power main supplying our properties. Does anyone know about
> this?
> He said the work order had the project staring tomorrow but he advised
> that normally means 5-10 days before they actually show up to do the work.
> Ron
> Sent from my iPhone
> _______________________________________________
> Everyone mailing list
> Everyone at chelseaplacedecatur.com
> https://chelseaplacedecatur.com/cgi-bin/mailman/listinfo/everyone
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://chelseaplacedecatur.com/pipermail/everyone/attachments/20260225/4bb519a9/attachment.htm>
More information about the Everyone
mailing list